Mooi
Iron Fuel Technology
15 October 2022 till 30 September 2026

From demo
to pilot.
In this project, we design, build and validate a 1 MW boiler and a 200 kW production system under real operating conditions. At the same time, we prthe supply chain, regulatory requirements and operational setup needed to move from demonstration to implementation. The objective is clear: remove the remaining technical and practical barriers so pilot projects can move forward with confidence.
Project progress
15-10-2022
Start date
30-09-2026
End date
Why it matters.
A successful demonstration is not enough to unlock industrial adoption. Before companies invest in pilot installations, the technology must prove reliability under real operating conditions and fit within existing supply chains, regulations and operational frameworks. Without this step, Iron Fuel remains a promising innovation. With it, commercialization become a viable next move.
Project partners




What we are working on.
System validation
Develop a dynamic system model and perform a Life Cycle Analysis to validatre technical and environmental impact.
Engineering & build
Design and realize a 1MW Iron Fuel Boiler and a 200 kW Iron Fuel Production sytem.
Develop a dynamic system model and perform a Life Cycle Analysis to validatre technical and environmental impact.
Engineering & build
Design and realize a 1MW Iron Fuel Boiler and a 200 kW Iron Fuel Production sytem.
Real- world demonstration
Install and test both systems under operational conditions to reach TRL7.
Market readiness
Align supply chain, regulatory frameworks and operational requirements to enable pilot deployment.
Install and test both systems under operational conditions to reach TRL7.
Market readiness
Align supply chain, regulatory frameworks and operational requirements to enable pilot deployment.